Tuesday, April 16, 2019

Progress Update: April 16th


(Eric and Penny building hatch rims)
  • The last of the galley flooring and all the aluminum rims for the access hatches are finished!
  • Eric is doing the last section of the galley overhead and rewiring each light fixture a bit at a time. 
  • We are also battling more plumbing leaks in the lower, forward area. There was a lot of water in the bilges and the leaks are coming from some plumbing fittimgs under the laundry room and in the water heater closet under the stairwell. We are giving thanks however that only one new access hatch will have to be cut. All the other areas had access hatches built two years ago. Also thankful we were able to empty and dry the bilges easily.