Friday, March 30, 2018

Progress Update: March 30th

 (Eric adjusting the cabin access hatch)

Almost finished with the guest cabin and head!
  • Aluminum trim has been installed around the access hatch in the head floor.
  • Mahogany trim was cut, fitted and installed in the head.
  • The shower port is caulked
  • The sink cabinet has been primed and painted
  • The carpet is installed in the cabin.











Friday, March 23, 2018

Progress Update: March 23rd

(Eric installing vinyl flooring)
 
  • Hot and cold plumbing runs have been hooked up under the sink and in the shower.
  • All the FRP wall and overhead panels have been installed in the guest head and shower. 
  • Teak trim was used in the shower and mahogany trim is currently being installed in the head.
  • Waterproof vinyl flooring has been installed in the head. Carpeting will be used in the main cabin.


















Sunday, March 11, 2018

Progress Update: March 11th

(Eric working on plumbing with Penny supervising)
  • The old plumbing has been removed in the forward guest head. New plumbing has been installed in the shower and underneath the floorboards. 
  • We replaced the shower faucets and a new sink vanity is in progress. The faucet is new but we were able to salvage the stainless steel sink. The counter is made of some scrap Corian.
  • The old head plumbing has been removed and will be replaced with new PEX.
  • The first two walls of FRP paneling have gone up with the shower opening cut out.



















Saturday, March 3, 2018

Progress Update: March 3rd


(Eric installing overhead panels)
  • The main guest cabin is close to completion. A new bench/storage area has been built, installed and painted. The overhead panels along with trim and seam covers were cut, fitted, painted and installed. 
  • The shower stall is next with plumbing currently underway. The wall was cut away around the faucets and holes drilled for PEX tubing.